Feedstock Study
Dammam / Eastern Province — Phase Initial · Registry: registry-dammam-v3 · May 2026
Eastern Province generates 3,486 TPD across nine streams — growing at 8.08% CAGR, the fastest waste market in the Kingdom. Ras Tanura petcoke ash (120 TPD from the world's largest oil terminal) is Saudi Arabia's primary V₂O₅ recovery site nationally. Phase Initial: 4 modules, 400 TPD, 140,000 tpy. Eastern Province ELT hotspot per Grand View Research.
Surge Capacity Design Basis
Refinery turnarounds at Ras Tanura and SAMREF generate +40% industrial waste volume for 4–8 week periods. Eid holiday surge adds +30%. Eastern Province baseline grows ~500 TPD/year at 8.08% CAGR — the design basis is already conservative relative to Year 5 volume. WARN-05 applies.
Stream Volume Table All ESTIMATED
| Stream | TPD | Annual (tpy) | Originator | Access | Phase | Primary ACM Output |
|---|---|---|---|---|---|---|
| MSW Residential | 1,882 | 658,700 | SEEC / Dammam Amanah | IMMEDIATE | Initial | Carbon Black RC2–RC3, Graphite RC3 |
| MSW Commercial | 696 | 243,600 | SEEC / SABIC EP | IMMEDIATE | Initial | Carbon Black RC2, Graphite RC3 |
| Petcoke / Coal Ash | 120 | 42,000 | Ras Tanura — Aramco Arabian heavy crude | CONDITIONAL | Initial | V₂O₅ PRIMARY · Ni · Ga — WARN-08 |
| End-of-Life Tires | 210 | 73,500 | EP hotspot — Grand View Research | IMMEDIATE | Initial | Carbon Black RC2–RC3, Aromatics RC3 |
| Contaminated Recycling | 210 | 73,500 | EP recycling centers | IMMEDIATE | Initial | Carbon Black RC2, Aromatics RC3 |
| ASR | 120 | 42,000 | ELECTA (SIRC) — Eastern Province | IMMEDIATE | Initial | Carbon Fiber Precursor RC4, Aromatics RC3 |
| Wastewater Sludge | 180 | 63,000 | Aramco Dhahran + Ras Tanura industrial WWTP | CONDITIONAL | Initial | Pozzolanic SCM RC2, industrial metals RC2 |
| C&D Fluff | 68 | 23,800 | Akam (SIRC) / Dammam construction | IMMEDIATE | Initial | Mineral Aggregate RC1, Carbon RC2 |
| Total Addressable | 3,486 | 1,220,100 | ESTIMATED | |||
| Phase Initial | 400 | 140,000 | LOCKED | |||
Ras Tanura Petcoke Ash — Saudi Arabia's Primary V₂O₅ Site
Ras Tanura is the world's largest oil terminal. Saudi Aramco's Arabian heavy crude — one of the most vanadium-rich crude grades commercially produced — generates petcoke that, when burned in industrial boilers, concentrates vanadium in fly ash at commercially recoverable levels. At 120 TPD, Dammam/Ras Tanura produces 6× the petcoke ash volume of Jubail Phase Initial and 2× that of Yanbu.
| Product | RevCon | Source | Export Ref. |
|---|---|---|---|
| Vanadium V₂O₅ | WARN-08 | Ras Tanura petcoke combustion | $8–12/kg — TBD volume |
| Nickel | RC2–RC3 MTL-011 | Co-concentrated with vanadium | $12–16/kg |
| Gallium | RC4 MTL-042 | Coal/industrial ash | $220–350/kg |
WARN-08: V₂O₅ recovery requires engineering confirmation for Ras Tanura petcoke configuration. On-site ash analysis required before V₂O₅ volumes are confirmed in any client document.
8.08% CAGR — Growth Context
Eastern Province is the Kingdom's fastest-growing waste market. At 8.08% CAGR, the baseline grows ~500 TPD per year:
| Year | Baseline TPD (ESTIMATED) | Phase Initial capacity | Capacity utilisation |
|---|---|---|---|
| 2026 (baseline) | 3,486 | 400 TPD | 11.5% |
| 2030 (COD) | ~4,770 | 400 TPD | 8.4% — Phase Medium timing |
| 2035 | ~6,600 | Phase Expanded needed | — |
Growth trajectory means Phase Initial (400 TPD) is conservative relative to Year 5 volume. Phase Medium (800 TPD) and Phase Expanded (1,200 TPD) are structurally required by the market, not speculative.
Key Operators
| Operator | Role | Stream |
|---|---|---|
| Saudi Aramco | Ras Tanura refinery + Dhahran complex | Petcoke ash 120 TPD (PRIMARY) + industrial sludge |
| SABIC | Eastern Province plants (ARSS, SHARQ, Petrokemya) | Commercial + industrial waste streams |
| SEEC | Eastern Province municipal waste | MSW residential + commercial |
| ELECTA (SIRC) | EoL vehicles → metals | ASR 120 TPD |
| MODON | Industrial estate authority | Site agreement — independent from SIRC CSA |
Infrastructure Map
Map initialising — requires Google Maps API key
Sources: SIRC.sa · RCJY.gov.sa · Marafiq.com.sa · MWAN.gov.sa · Verification: May 2026